Construction Schedule

Phase timeline and progress tracking across all projects

Total Phases

15

Completed

7

In Progress

3

Overall Progress

47%
ProjectPhaseDescriptionStartEndResponsibleDepends OnStatusNotes
Casa Monteiro RenovationDemolitionRemove existing flooring, partitions, fixtures2026-01-272026-02-05Construtora Vega
Casa Monteiro RenovationMasonry & PlumbingNew walls, plumbing rough-in2026-02-062026-02-20Construtora Vegasph-001
Casa Monteiro RenovationElectrical Rough-InFull rewiring, new distribution board2026-02-102026-02-24Elétrica Pradosph-001
Casa Monteiro RenovationPlasteringAll walls and ceilings plastered and primed2026-02-252026-03-10Construtora Vegasph-002
Casa Monteiro RenovationFlooringEngineered hardwood and porcelain installation2026-03-112026-03-22Construtora Vegasph-004
Casa Monteiro RenovationPaintingFull apartment painting2026-03-182026-04-02Pintura Castelosph-004Bedrooms in progress
Casa Monteiro RenovationCarpentryKitchen island, closet, TV panel2026-03-252026-04-18Marcenaria Formasph-005
Casa Monteiro RenovationStone WorkCountertops and vanity tops2026-04-142026-04-22Marmoraria Nobresph-007
Casa Monteiro RenovationLighting FinishFixture installation, dimmers2026-04-152026-04-25Elétrica Pradosph-007
Casa Monteiro RenovationFurniture & StylingDelivery, placement, final styling2026-04-282026-05-10Camila Pereirasph-008
Casa Monteiro RenovationHandoverPunch list, walkthrough, handover2026-05-122026-05-15Camila Pereirasph-010
Studio LoftDemolitionRemove partitions and old fixtures2026-03-032026-03-08Construtora Urban
Studio LoftConstruction WorksMasonry, electrical, plumbing2026-03-092026-03-28Construtora Urbansph-012
Studio LoftFinishes & FlooringPolished concrete, painting2026-03-292026-04-15Construtora Urbansph-013
Studio LoftFurniture & HandoverFurniture delivery and handover2026-04-202026-04-28Camila Pereirasph-014